The UK Energy Problem Open the explorer

At today’s build rate, Britain runs short of power from 2031.

Demand for electricity is set to almost double by 2040. Britain is building wind, solar and firm power far too slowly to keep up, and plants ordered today will not arrive until the 2030s. This independent model measures the gap and tests two ways of closing it.

Demand pathway

Showing NESO’s central pathway, Holistic Transition.

Firm power Britain would be short of under current policy

Extra dispatchable capacity needed to meet the official reliability standard of no more than 3 hours a year without enough power.

Firm power shortfall under current policy at today’s build rate, 2030 to 2050.
  • Current policy

    Wind, solar and batteries built at today’s pace. Gas replaced like-for-like. Nothing else added.

    2030–50, incl. grid

    Explore this plan
  • Current policy delivered

    The same policy built fast enough to work: Clean Power 2030 pace to 2050, plus gas back-up.

    2030–50, incl. grid

    Explore this plan
  • Nuclear buildout

    Small modular reactors from 2039 and one large reactor, with gas and coal back-up while they arrive.

    2030–50, incl. grid

    Explore this plan

Real 2024 pounds, generation, storage, fuel and grid. Current policy looks cheapest only because it does not keep the lights on: the model puts no price on electricity that is not supplied.

Why this matters

  • Demand is set to surge. In NESO’s central pathway demand nearly doubles, from about 291 TWh in 2025 to 564 TWh in 2040, as vehicles and heating switch to electricity.
  • AI computing comes on top. By mid-2025 about 140 data centres, seeking roughly 50 GW, were queuing for grid connections. Our highest case plans for about 101 TWh a year by 2035 (why we chose that figure).
  • Meeting that demand matters for growth. AI is set to be critical to economic growth. Services make up about 79% of the UK economy, and for a services economy like Britain’s, being able to power AI computing at home will be key to staying competitive.
  • Wind and solar need firm back-up. In cold, still weeks renewable output stays low for days. NESO has issued seven capacity margin warnings this year.
  • Lead times are long. Gas turbine order books are full four to five years ahead and a new combined-cycle station takes five to seven years. Plants needed in the mid-2030s have to be ordered now.

Figures: NESO Future Energy Scenarios 2025 and Ten Year Outlook 2026; Ofgem connections review, February 2026; ONS Index of Services; S&P Global, October 2026; manufacturer order books reported in 2026. Links are in the audit report.

1 · Current policy

If nothing changes

Counting the projects now under construction, Britain is building about 2.2 GW of offshore wind, 0.55 GW of onshore wind and 1.9 GW of solar a year. That is roughly a quarter to two-fifths of the pace Clean Power 2030 needs. This plan carries that pace forward, with Sizewell C, the Wylfa reactors and the storage and interconnectors already in the pipeline, and replaces retiring gas stations like-for-like. Nothing else is added.

GW added a year2021–25 averagePace now, with projects under constructionClean Power 2030 needsTimes faster
Offshore wind1.252.26.53.0×
Onshore wind0.470.552.34.2×
Solar1.631.94.82.5×
Batteriesabout 1.523.61.8×
Year-by-year additions and sources
GW added a year20212022202320242025Average 2021–25Under construction nowPace used in current policyClean Power 2030 paceShortfall
Offshore wind0.872.590.891.410.511.2511.85 GW2.26.53.0×
Onshore wind0.420.350.690.670.230.472.04 GW0.552.34.2×
Solar0.480.562.761.862.491.633.2 GW1.94.82.5×
Batteriesabout 1.5 a year (6.8 GW operating at end-2025)1.59.9 GW23.61.8×

Pace used in current policy = 2021–25 additions plus projects now under construction, averaged over 2021–28 (solar about 2.4 GW a year to 2028, then 1.9). Shortfall = how many times faster Clean Power 2030 needs Britain to build. Sources: DESNZ Energy Trends table 6.1 (installed capacity, year end), Renewable Energy Planning Database Q2 2026 (under construction), Modo Energy (batteries) and the Clean Power 2030 Action Plan.

Not enough power. Under central demand, Britain is about GW short of firm power in 2035, GW in 2040 and GW in 2050. Expected shortfalls reach hours a year by 2050, against a standard of 3.

This is a planning model. It tests whether enough capacity exists, not the day-to-day operational warnings NESO issues, which this year came mostly from summer heat, plant availability and forecast errors.

2 · Current policy delivered

If the build problem is solved but policy stays the same

This is the best case for the current approach. Wind, solar and batteries are built at the Clean Power 2030 pace every year to 2050, gas is replaced like-for-like, and gas engines and open-cycle turbines are added, as fast as they can be delivered, to meet the 3-hour standard. Beyond Sizewell C and Wylfa, no new nuclear, carbon capture or hydrogen is assumed, because almost none is being built.

Gigawatts a year, built now and needed (average 2031–50)

Built nowNeeded

That has to be sustained for twenty years, plus about GW of new gas engines and open-cycle turbines by 2050. The cost is scale. Wind and solar cannot cover long, cold, still spells and four-hour batteries cannot bridge them, so the system still needs gas back-up for those weeks, while much of the extra wind and solar arrives when there is already a surplus: about TWh is switched off in 2050.

Total cost over 2030–50, including grid connections and network upgrades: £bn.

What about carbon capture?

If the new combined-cycle stations were also fitted with carbon capture, their output would count as clean and this plan would reach about 98% by 2050, at an approximate additional cost of £100bn. It is too early to know that cost with enough precision to model: Britain’s first gas station with carbon capture, Net Zero Teesside Power (742 MW, about £4bn), is not due to start until 2028, and transport, storage and support costs have not been published. The figure scales Teesside’s cost per gigawatt to the plan’s 23 GW of new combined-cycle stations, so it is an indication, not a modelled result.

Figures for central demand.

3 · Nuclear buildout

A different plan

The nuclear buildout keeps the renewables already built or contracted but adds no more. Instead it builds a fleet of small modular reactors from 2039 and one large reactor in 2037, rising to about GW of nuclear by 2050, with gas engines, open-cycle turbines and four coal stations as back-up while the reactors arrive. It is sized to the same 3-hour standard.

Total cost over 2030–50, including grid: £bn, about £bn less than delivering current policy, because reactors on existing sites need far less new grid and run whatever the weather.

The three plans side by side

Showing . Change the pathway at the top of the page.

Total cost 2030–50

Generation, storage and fuelGrid
Current policyCurrent policy deliveredNuclear buildout

*Current policy looks cheapest only because it does not keep the lights on. Over the whole period the nuclear buildout emits more CO₂ than current policy delivered because its reactors arrive through the 2030s and 2040s and it relies on gas and some coal until they do. Real 2024 pounds, undiscounted.

How much AI demand are we planning for?

The AI expansion demand case plans for about 101 TWh a year of data-centre demand by 2035: the 41 TWh in NESO’s higher pathway plus 60 TWh more, or about 11.5 GW running day and night. It is built on that higher pathway, with its vehicle and heating mandates, so it shows the most demand Britain should plan for. It is a planning choice, not a forecast, and it is above every NESO estimate. The other three pathways are NESO’s own, so the finding that current plans fall short does not depend on it.

The evidence, the estimates and why we plan for about 101 TWh

The evidence

  • The government’s own forecast. The UK Compute Roadmap (July 2025) forecasts that Britain “will need at least 6GW of AI-capable data centre capacity by 2030”, three times today’s data-centre capacity. Run at 75–95% of capacity, 6 GW is roughly 40–50 TWh a year, around double NESO’s central 2030 figure for all data centres (23 TWh), and it is for 2030, not 2035. The roadmap does not say whether 6 GW is computing load or whole-site capacity including cooling, so the TWh figure is approximate.
  • Independent evidence to Parliament. LSE’s Centre for Economic Transition Expertise used a stylised 10 GW at 90% use, which is 79 TWh a year, with a 20 GW high case. Our 101 TWh sits between the two.
  • The connection queue. By mid-2025 about 140 data centres were seeking roughly 50 GW of grid connections. NESO judges that close to half of pipeline capacity may be highly speculative or duplicative, but even a modest share would be very large.
  • US forecasters keep revising up. BloombergNEF expects US data-centre demand to reach 106 GW by 2035, up from about 25 GW operating in 2024. That forecast is 36% higher than its own estimate eight months earlier. NERC, the North American grid reliability body, now expects peak demand to rise by over 224 GW in ten years, 69% more than it projected a year before, with data centres accounting for most of the increase. US national load forecasts have now been revised up for three years running.
  • NESO’s latest view is lower. Its September 2026 Ten Year Outlook cut data-centre demand to about 15 TWh in 2031 and 24 TWh in 2036 (about 22 TWh in 2035), citing updated utilisation data and project attrition. That is well below its own 2025 scenarios and far below the government’s 6 GW forecast. The two official views now differ by a factor of two to three, which is why we plan for the higher end rather than the lower.
EstimateData-centre demandYear
NESO Ten Year Outlook 2026 (latest, revised down)about 22 TWh2035
NESO 2025 ten-year forecast (before the cut)33 TWh2035
NESO 2025 scenarios, lower (Falling Behind)20 TWh2035
NESO 2025 scenarios, central (Holistic Transition)37 TWh2035
NESO 2025 scenarios, higher (Electric Engagement)41 TWh2035
Government 6 GW forecast, at 75–95% use40–50 TWh2030
LSE stylised case, 10 GW at 90%79 TWh—
Our AI expansion case101 TWh2035
LSE high case, 20 GW at 90%about 158 TWh—

Why we plan for about 101 TWh

  1. The government’s forecast already exceeds every NESO figure, and it is a 2030 minimum. It implies tripling capacity in five years. If growth continues after 2030, demand in 2035 will be higher still.
  2. Forecasters have repeatedly underestimated this demand. In the US, the main forecasts have been revised up year after year as data-centre orders arrived faster than expected. NESO has moved the other way, cutting its figure for 2035 from 33 TWh to about 22 TWh. We would rather plan for the upward trend seen in the largest market than assume Britain will be the exception.
  3. It sits inside the independent range: just above LSE’s 10 GW case and well below its 20 GW high case.
  4. Government policy is trying to attract computing investment, including faster grid connections for data centres. The supply plan has to be sized for that policy succeeding.
  5. The risks are not symmetric. Firm power takes five to seven years or more to deliver. Planning too low means investment goes elsewhere and the grid runs short. Planning too high means some capacity is built early. Large loads that bring their own firm power reduce the public requirement one for one, so if demand arrives with its own power, the public plan shrinks.

The 60 TWh step is a round planning increment, not derived from any one source, and full effect by 2035 is ambitious given connection and equipment lead times. It would make data centres about 20% of British electricity demand in 2035, a similar share to Ireland today and above the 9.5–15% US federal researchers project for the US in 2030. Some US forecasters also judge utility projections to be overstated. Treat 101 TWh as the upper planning case. The explorer shows NESO’s lower pathways alongside it. Sources: DSIT, UK Compute Roadmap, July 2025, section 4.2; LSE CETEx written evidence DCU0046; NESO Future Energy Scenarios 2025; NESO, Ten Year Outlook 2026 briefing to the Electricity Markets Advisory Council, 22 September 2026 (slides 15–17); BloombergNEF via Utility Dive, December 2025; NERC Long-Term Reliability Assessment, January 2026; Grid Strategies, National Load Growth Report 2025; LBNL, US Data Center Energy Usage Report, June 2026.

Checked against NESO

Run on the 2030 system in NESO’s Clean Power 2030 advice, with NESO’s capacities and assumptions, the model reproduces NESO’s results.

2030NESOThis model
Renewables share of generation77–82%78%
Gas power stations14–15 TWh16 TWh
Clean share95%95%
Reliability standard (3 hours)MetMet (0.3 h)

Source: NESO, Clean Power 2030 advice (November 2024), Further Flex and Renewables pathway. Method and results: model file v2/benchmark/benchmark_neso.json.

Method and evidence

The model is built on over 1,000 documented assumptions from about 100 cited sources and a record of nearly 3,000 existing power stations. For every year from 2030 to 2050 it replays each hour across seven historical weather years and two severe cold spells, with and without trade with Europe, and tests each plan against the official 3-hour reliability standard with random power station breakdowns. Grid connections and wider network upgrades are costed alongside generation, storage and fuel.

All three plans include the interconnectors already approved (rising to about 14.5 GW by 2033), Ofgem’s 16 provisionally selected long-duration storage projects (7.6 GW) and the current limit on moving power from Scotland to England. They narrow the gap but do not close it.

In the explorer the three plans are fully calculated for all four demand pathways. You can edit a plan’s build orders and see capacity and construction spending change straight away. Hour-by-hour results for an edited plan need the full model, which runs on your own computer.

Caveat. More interconnection, storage and flexible demand would let more of the surplus be used. Version 2 includes the interconnectors and storage already approved. Going further adds cost, and in Europe-wide cold, still spells neighbouring countries have less to spare: the government's expert panel on NESO's 2026 capacity report identifies low wind with high European demand as "evidently the key risk case for GB" (Panel of Technical Experts, 2026, para. 107).