The UK Energy Problem

An interactive model of Britain’s electricity system measuring how far current plans fall short and modelling how to close the gap.

Model version 2.7 (public version 2) · updated 24 October 2026

Why we built this

Electricity demand is set to almost double by 2040, but current plans don’t provide enough power for cold, still winter days and the plants needed to address that take years to build, so Britain risks running short from the early 2030s. We built the model to test options for solving that problem and to understand how big and how urgent it is.

The model's own results underline the urgency. At the rate Britain is actually building, and even with the storage and interconnectors already in the pipeline, current plans miss the 3-hour reliability standard from the early 2030s under every NESO demand pathway (see below). Plants needed then take five to seven years or more to deliver, so they have to be ordered now.

Figures: NESO Future Energy Scenarios 2025 (ED1 data table) and Ten Year Outlook 2026; Ofgem connections review, February 2026; S&P Global, October 2026; manufacturer order books reported in 2026. Details and links are in the audit report.

Open the explorer

What the model covers

The model is built on over 1,000 documented assumptions drawn from 100 cited sources and a record of nearly 3,000 existing power stations. For every year from 2030 to 2050, it replays each hour of the year across seven historical weather years and two severe cold-spell scenarios, with and without electricity trade with Europe, giving a total of 567 simulated years for each plan. A further 1,764 simulated years, with random power station breakdowns, test each plan against the official 3-hour reliability standard. Together these produce around 600 calculated results per year, from generation and costs to fuel use, emissions and supply shortfalls and over 12 million stored results.

Version 2 adds an estimate of the cost of new grid connections and wider network upgrades, including projects already under construction, shown alongside generation, storage and fuel. Over 2030–50 in the central case it adds about £361bn to current policy delivered, against about £173bn for the nuclear buildout, because offshore wind needs far more new grid than plant built on existing power station sites.

In the model, no plan that relies on wind, solar and unabated gas reaches 95% clean while keeping the lights on. Even building wind, solar and batteries at the Clean Power 2030 pace to 2050 reaches only about 90%. Holding gas to 5% leaves demand unmet, whilst letting it run to keep the lights on breaks the 95% commitment. Carbon capture on the new gas stations would close most of the difference, at an approximate additional cost of £100bn, but very little is planned and its cost is too uncertain to model. Only the nuclear buildout reaches 95% clean, by 2050, while meeting the reliability standard.

Version 2 also includes the interconnectors already approved (rising from 10.3 GW today to about 14.5 GW by 2033), Ofgem’s 16 provisionally selected long-duration storage projects (7.6 GW, 2029–2033) and the current limit on moving power from Scotland to England. Together they cover the gap until the mid-2030s. After that the shortages come when Europe is also short, and in cold, still spells lasting several days, longer than the new storage can run. They narrow the gap but do not close it.

1. If nothing changes

The explorer opens on current policy as Britain is actually delivering it. Over 2021–25 Britain added on average about 1.3 GW of offshore wind, 0.5 GW of onshore wind and 1.6 GW of solar a year. Counting the projects now under construction, the recent pace is about 2.2 GW of offshore wind, 0.55 GW of onshore wind and 2 GW of solar a year: roughly a quarter to two-fifths of the pace Clean Power 2030 needs. This plan carries that pace forward, with Sizewell C and the planned Wylfa reactors, the long-duration storage and interconnectors already in the pipeline, and a gas fleet kept near today’s 35 GW by replacing older stations like-for-like. Nothing else is added.

How fast Britain is building

GW added a year20212022202320242025Average 2021–25Under construction nowPace used in current policyClean Power 2030 paceShortfall
Offshore wind0.872.590.891.410.511.2511.85 GW2.26.53.0×
Onshore wind0.420.350.690.670.230.472.04 GW0.552.34.2×
Solar0.480.562.761.862.491.633.2 GW1.94.82.5×
Batteriesabout 1.5 a year (6.8 GW operating at end-2025)1.59.9 GW23.61.8×

Pace used in current policy = 2021–25 additions plus projects now under construction, averaged over 2021–28 (solar about 2.4 GW a year to 2028, then 1.9). Shortfall = how many times faster Clean Power 2030 needs Britain to build. Sources: DESNZ Energy Trends table 6.1 (installed capacity, year end); Renewable Energy Planning Database, Q2 2026 (under construction); Modo Energy (batteries); Clean Power 2030 Action Plan.

Britain would not have enough electricity, and would miss its carbon target.

Not enough power: hours a year when supply falls short

Hours a year without enough power under current policy at today’s build rateExpected hours a year when supply falls short, 2030 to 2050, for three demand pathways, against the 3-hour reliability standard. Central: 2030 2 h, 2035 33 h, 2040 319 h, 2045 888 h, 2050 1,321 h.05001,0001,5002,00020302035204020452050hoursStandard: 3 hLower · 451 hCentral · 1,321 hHigher · 1,923 h

The reliability standard allows 3 hours a year. Under current policy at today’s build rate the standard is missed from 2031 in the central case, in 20 of the 21 years to 2050.

Extra firm power needed to meet the 3-hour reliability standard

Extra firm power needed to meet the 3-hour reliability standardGas-engine capacity that, added to current policy at today’s build rate, meets the 3-hour standard. Central: 2030 0 GW, 2035 8 GW, 2040 25 GW, 2045 36 GW, 2050 44 GW.010203040506020302035204020452050GWLower · 33 GWCentral · 44 GWHigher · 59 GW

Gap = the gas-engine capacity that, added to current policy at today’s build rate, brings expected shortfalls down to the 3-hour standard. Firm plant takes five to seven years or more to deliver.

Carbon target missed: clean share of electricity

Clean share of electricity under current policy at today’s build rateShare of generation from clean sources, central demand. Current policy: 68% in 2030, 75% in 2040, 71% in 2050, against the 95% target.6070809010020302035204020452050%95% targetCurrent policy · 71%

Share of electricity generated from clean sources (renewables, nuclear and other low-carbon), central demand. Clean Power 2030 targets 95%.

2. If the build problem is solved but policy stays the same

Current policy delivered is the best case for the current approach. Wind, solar and batteries are built at the Clean Power 2030 pace every year to 2050, gas is replaced like-for-like, and gas engines and open-cycle turbines are added until the 3-hour standard is met in every demand case. No new nuclear, carbon capture or hydrogen is assumed, because almost none is being built.

Build rate: gigawatts a year, today versus what current policy needs

Build rate: today versus what current policy needs, GW a yearAverage gigawatts a year, 2031 to 2050, central demand. offshore wind: 2.2 now, 6.6 needed; onshore wind: 0.6 now, 2.6 needed; solar: 1.9 now, 4.8 needed; batteries: 2.2 now, 4.6 needed.Built nowNeededOffshore wind2.2 GW6.6 GWOnshore wind0.6 GW2.6 GWSolar1.9 GW4.8 GWBatteries2.2 GW4.6 GWGas engines and turbinesNone0.9 GW

Average a year, 2031–50, central demand. Sustained for twenty years, plus about 19 GW of new gas engines and open-cycle turbines by 2050.

That is three times today’s offshore wind rate, nearly five times onshore and two and a half times solar. It keeps the lights on, meeting the 3-hour standard every year in every demand case. But it still misses the carbon target.

Clean share: the target is still missed

Clean share if the build problem is solved but policy stays the sameShare of generation from clean sources, central demand. Current policy delivered reaches 90% in 2050; with carbon capture on its new gas stations about 96%.6070809010020302035204020452050%95% targetToday’s pace · 71%Delivered · 90%+ carbon capture · 96%

Central demand. Dashed line: the same plan if its new combined-cycle gas stations were fitted with carbon capture.

Wind and solar cannot cover long, cold, still spells and four-hour batteries cannot bridge them, so extra turbines mostly add output when there is already a surplus: about 263 TWh is switched off in 2050. The clean share stops at about 90%. Total cost over 2030–50, including grid connections and network upgrades, is about £1,666bn.

Carbon capture. If the new combined-cycle stations were fitted with carbon capture, their output would count as clean and this plan would reach about 96% by 2050, at an approximate additional cost of £100bn. It is too early to know that cost with enough precision to model: Britain’s first gas station with carbon capture, Net Zero Teesside Power (742 MW, about £4bn), is not due to start until 2028, and transport, storage and support costs have not been published. The figure scales Teesside’s cost per gigawatt to the plan’s 23 GW of new combined-cycle stations, so it is an indication, not a modelled result.

3. A different plan: the nuclear buildout

The nuclear buildout keeps the renewables already built or contracted but adds no more. Instead it builds a fleet of small modular reactors, from 2039, and one large reactor in 2037, rising to about 50 GW of nuclear by 2050, with gas engines, open-cycle turbines and four coal stations as backup while the reactors arrive. It is sized to the same 3-hour standard and meets it every year in every demand case. It reaches about 96% clean by 2050 in the central case and costs about £1,195bn over 2030–50 including grid, £471bn less than delivering current policy, because reactors on existing sites need far less new grid and run whatever the weather.

The three plans compared

Clean share of electricity, three plans

Clean share of electricity, three plansShare of generation from clean sources, central demand, 2050: current policy 71%, current policy delivered 90%, nuclear buildout 96%.6070809010020302035204020452050%95% targetCurrent policy · 71%Delivered · 90%Nuclear · 96%

Central demand. Only the nuclear buildout reaches 95% while keeping the lights on.

Total cost 2030–50, including grid

Total cost 2030 to 2050, three plansCentral demand, real 2024 pounds. Current policy £1,079bn, current policy delivered £1,666bn (about £1,766bn with carbon capture), nuclear buildout £1,195bn.Generation, storage, fuelGridCarbon capture, approx.Current policy*£1,079bnCurrent policy delivered£1,666bnDelivered + carbon capture£1,766bnNuclear buildout£1,195bn

*Current policy looks cheapest only because it does not keep the lights on: the model puts no price on electricity that is not supplied. Carbon capture cost is an approximate indication, not modelled. Real 2024 pounds, central demand.

Central demand, 2030–50Current policyCurrent policy deliveredNuclear buildout
Meets the 3-hour standard?No, from 2031Yes, every yearYes, every year
Expected shortfall, 2050 (standard 3 hours)1,321 hUnder 3 hUnder 3 h
Clean share, 205071%90% (about 96% with carbon capture)96%
Generation, storage and fuel cost£938bn£1,305bn£1,021bn
Grid connections and network upgrades£141bn£361bn£173bn
Total£1,079bn£1,666bn (about £1,766bn with carbon capture)£1,195bn
CO₂ 2030–501,036 Mt642 Mt820 Mt

Over the whole period the nuclear buildout emits more CO₂ than current policy delivered (820 against 642 Mt), because its reactors arrive through the 2030s and 2040s and it relies on gas and some coal until they do; by 2050 it is the cleaner system. The range across demand cases is in the explorer.

Caveat. More interconnection, storage and flexible demand would let more of the surplus be used. Version 2 includes the interconnectors and storage already approved; going further adds cost, and in Europe-wide cold, still spells neighbouring countries have less to spare: the government's expert panel on NESO's 2026 capacity report identifies low wind with high European demand as "evidently the key risk case for GB" (Panel of Technical Experts, 2026, para. 107).

Solving the problem

We are so far behind in energy generation, that this problem cannot be solved by supply side changes alone. We are simply too far behind to be pursuing EV targets for vehicles and converting to heat pumps whilst supporting an industrial strategy and widespread AI adoption. Priority to AI buildout and economic growth has to come above other demands for power generation. These models assume there is at least some reform to improve the current planning timelines.

How much AI demand are we planning for?

The AI expansion demand case plans for about 97 TWh a year of data-centre demand by 2035: NESO’s central 37 TWh plus 60 TWh more, or about 11 GW running day and night. It is a planning choice, not a forecast, and it is above every NESO estimate. The gap chart above uses NESO’s own pathways, so the finding that current plans fall short does not depend on it.

The evidence

EstimateData-centre demandYear
NESO Ten Year Outlook 2026 (latest, revised down)about 22 TWh2035
NESO 2025 ten-year forecast (before the cut)33 TWh2035
NESO 2025 scenarios, lower (Falling Behind)20 TWh2035
NESO 2025 scenarios, central (Holistic Transition)37 TWh2035
NESO 2025 scenarios, higher (Electric Engagement)41 TWh2035
Government 6 GW forecast, at 75–95% use40–50 TWh2030
LSE stylised case, 10 GW at 90%79 TWh—
Our AI expansion case97 TWh2035
LSE high case, 20 GW at 90%about 158 TWh—

Why we picked 97 TWh

  1. The government’s forecast already exceeds every NESO figure, and it is a 2030 minimum. It implies tripling capacity in five years. If growth continues after 2030, demand in 2035 will be higher still.
  2. Forecasters have repeatedly underestimated this demand. In the US, the main forecasts have been revised up year after year as data-centre orders arrived faster than expected. NESO has moved the other way, cutting its figure for 2035 from 33 TWh to about 22 TWh. We would rather plan for the upward trend seen in the largest market than assume Britain will be the exception.
  3. It sits inside the independent range: just above LSE’s 10 GW case and well below its 20 GW high case.
  4. The reforms are designed to attract computing investment, through faster connections and routes for large loads to bring their own power. The supply plan has to be sized for that policy succeeding.
  5. The risks are not symmetric. Firm power takes five to seven years or more to deliver. Planning too low means investment goes elsewhere and the grid runs short; planning too high means some capacity is built early. Large loads that bring their own firm power reduce the public requirement one for one, so if demand arrives with its own power, the public plan shrinks.

The 60 TWh step is a round planning increment, not derived from any one source, and full effect by 2035 is ambitious given connection and equipment lead times. It would make data centres about 22% of British electricity demand in 2035, a similar share to Ireland today and above the 9.5–15% US federal researchers project for the US in 2030; some US forecasters also judge utility projections to be overstated. Treat 97 TWh as the upper planning case; the explorer shows NESO’s lower pathways alongside it. Sources: DSIT, UK Compute Roadmap, July 2025, section 4.2; LSE CETEx written evidence DCU0046; NESO Future Energy Scenarios 2025; NESO, Ten Year Outlook 2026 briefing to the Electricity Markets Advisory Council, 22 September 2026 (slides 15–17); BloombergNEF via Utility Dive, December 2025; NERC Long-Term Reliability Assessment, January 2026; Grid Strategies, National Load Growth Report 2025; LBNL, US Data Center Energy Usage Report, June 2026.

Using the explorer: what is instant and what needs a run

Instant

  • Fully calculated plans: current policy at today’s build rate, current policy delivered and the nuclear buildout, under four demand pathways: NESO’s three and AI expansion. The explorer opens on current policy.
  • For each, year by year to 2050: capacity, generation, imports, fuel use, emissions, costs, supply checks across seven weather years and two cold-spell stresses, and hours against the 3-hour reliability standard.
  • If you edit a plan's build orders, its fleet, construction timetable and construction spending update immediately.

Needs a model run

  • Hour-by-hour results for an edited plan: generation, shortfalls, reliability hours, fuel, emissions and running costs.
  • These show as "Hourly recalculation required", so out-of-date figures are never displayed.
  • You can save an edited plan from the explorer as a file and open it again later. I may add the python script later so users can build their own plans and save.

Explore the model

Start from current policy and its gap, then compare delivering current policy in full with the nuclear buildout across four demand pathways: capacity, generation, costs and security of supply, including the 3-hour reliability standard.

Open the explorer

Methods and evidence

The audit report sets out every method, source and assumption. The workbook lists the inputs and results.

Audit report Workbook