Conditional life extension, constrained new gas procurement and a staged coal operating policy are tested against the same demand, nuclear, renewables, storage, trade and electrolysis assumptions. The study tests connected electricity supply. Fuel supply remains a separate condition.
How retention is represented
The five-year case retains75% of eligible named CCGT capacity after an assumed inspection programme. It uses85% availability,54% full-load efficiency, a25% refurbishment-year outage allowance,£150/kW refurbishment expenditure per five-year tranche and£10/kW/year extra fixed maintenance. These are conditional analyst estimates, anchored to published refurbishment evidence.
The ten-year sensitivity uses80% availability,52% efficiency,£250/kW per tranche and£15/kW/year extra O&M. A second overhaul and inspection are paid for after five years. Unknown forecast residuals, small peakers and ambiguous pre1990site dates receive no extension. No operator-approved station list is implied.
Original inherited-gas capital recovery has ended before the estimated40-year retirement boundary. Retention pays for refurbishment, maintenance and fuel; it does not incur a hypothetical new-plant capital annuity. Refurbishment borrowing uses the same4.5% real rate as the plan, with five-year recovery. Construction cash is reported separately and is not added again to annual capital recovery.
Coal can have mixed objectives
Up to4 GW nameplate—two station equivalents—is regularly committed through2044. Remaining coal follows an economic schedule. From2045 all coal moves to reserve duty: gas, scheduled imports and storage cover demand first, while coal starts in anticipation of residual needs under the existing ramp/start model.
The late six-station case adds units in2039/2040 under the original one-station-per-year limit. The early six-station case adds units in2035/2036 and explicitly raises the coal envelope to two stations/year. The latter tests a stronger construction assumption; it does not secure suppliers, sites, finance, domestic mining or logistics. The existing domestic coal supply assumption remains unchanged.
Procurement, fuel and interpretation
Slow cases allow at most2 new CCGTs/year with a five-year order-to-online lead,1.5 GW engines/year and0.9 GW open-cycle turbines/year, with a shared4.24 GW annual ceiling. No discretionary orders precede2029. Fast controls retain the earlier4 CCGT/4GWengine/7.36 GW shared envelope. These are procurement sensitivities, not measured global manufacturing limits.
The engine/OCGT ladder and CCGT reductions are bounded heuristics. Every final dated candidate is tested against7 historical-weather profiles and2 synthetic28-daycold/low-wind/nuclear-outage stresses for each year2030–2050. No stress probability, dynamic frequency certification or global least-cost optimum is claimed.
Costs cover generation, storage and bounded trade. Separate new planning/grid connections, wider networks, retail, complete fiscal settlements and fuel-security infrastructure remain outside the headline subtotal. Carbon and support payments are separate transfers.